Please can you confirm In which Functional setup Manager task is Next Purchase Order Number set up? Is it B or D?

A. Manage Common Options for Payables
B. Configure Procurement Business Function
C. Define a sequence for auto numbering and assign it back in Configure BU numbering setup
D. Configure Requisitioning Business Function

Accepted Answer

Saturday, June 11 2016, 07:10 AM - #Permalink
0
Purchase Order numbering is configured under Manage Purchasing Document Number task under FSM, Separate Document numbering can be defined for each Business Unit. Option B is the correct option.
The reply is currently minimized Show
Responses (1)
  • Accepted Answer

    Saturday, June 11 2016, 05:32 AM - #Permalink
    0
    It should be Option C
    The reply is currently minimized Show